WorkplanTillFinalPublication
Contents
Workplan Till Final Publication
When documents are staged, please update urls on publication request page PublicationRequestApril30
Rec-track Documents
No editing, except spelling mistakes.
April 23: hard deadline for final staging
- prov-o:
- pre-staged copied from PR will become dated when ready for Denis to take it.
- Added changes appendix
- Final staging April 11 to suit the rest of the Rec docs.
- pre-staged copied from PR will become dated when ready for Denis to take it.
- prov-dm: final staging: April 11 (luc non available 13-21)
- prov-n: final staging: April 11 (luc non available 13-21)
- prov-constraints: final staging: April 11 (luc non available 13-21)
Note-track Documents
for each document, please complete the following template
prov-xyz template
- Outstanding issues on tracker:
- Document ready for internal review:
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by:
- Changes incorporate by:
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
prov-primer
- Outstanding issues on tracker:
We do not anticipate any changes to the primer from the open issues below, but this depends partly on reviewer acceptance of proposed responses.
- Issues 561, 562, 563 and 564 are addressed and responded to but require approval/confirmation/closure by commenter
- Issue 592 is still to be addressed, but is not going to alter the primer, instead being addressed in the FAQ (as agreed by the group)
- Issue 616 has been addressed and agreed with the commenter (adopting a suggestion), and so can be closed
- Document ready for internal review: 29 March
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by: 4 April
- Changes incorporate by: 11 April
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
prov-xml
- Outstanding issues on tracker: Issues
- Document ready for internal review: 2013-03-28
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by: 2013-04-04
- Changes incorporate by: 2013-04-15
- Final vote: 2013-04-18 (last teleconference before staging deadline)
- Final staging: 2013-04-23
prov-aq
- 2013-03-14: issues triaged (resolved / further change needed / out-of-scope).
- 2013-03-21: resolved outstanding issues; document updated to reflect issues consensus; call for final reviews (2 week period).
- 2013-04-04: all review comments clarified and/or resolved.
- 2013-04-11: update spec for resolved issues arising from reviews.
- 2013-04-18: document clean, all issues closed, ready for staging.
- 2013-04-23; Final staging
prov-overview
Note I'm under the assumption that there will not be anything radical added to the document.
- 2013-03-14: call for review ask for additions
- 2013-03-28: end of additions
- 2013-04-04: all additions done sent for last looks
- 2013-04-23; Final staging
prov-dc
- Outstanding issues on tracker: None (we haven't received any feedback from the DC side on the last release)
- Document ready for internal review: 2013-03-28
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by: 2013-04-04
- Changes incorporate by:2013-04-15
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
prov-dictionary
- Outstanding issues on tracker: 10 ( http://www.w3.org/2011/prov/track/products/19 )
- Document ready for internal review: March 28
- Reviewers: Luc & Simon (both received)
- Reviews complete by: April 4
- Changes incorporate by: April 17
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
prov-sem
- Outstanding issues on tracker:
There are two: one a placeholder for an external reviewer comment on PROV-CONSTRAINTS, another about the scope/goal of PROV-SEM. Both have been discussed but not addressed in the document yet. I will initiate discussion to ensure that they are addressed in the review version.
- Document ready for internal review: April 8
- Reviewers: please volunteer, to be finalized at teleconference on April 4. Hopefully most of Satya, Simon, Luc, Paolo, Khalid who reviewed the first release.
- Reviews complete by: April 11
- Changes incorporate by: April 15
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
prov-links
We do not anticipate any significant change to the document. Just a read-through by the editors, and updating of sotd/bibliography.
- Outstanding issues on tracker: none
- Document ready for internal review: March 28
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by: April 4
- Changes incorporated by: April 11
- Final vote: 11 April 2013 (last teleconference before staging deadline)
- Final staging: 12 April 2013 (luc non available 13-21)
prov-implementations
We note there are no major changes needed for the implementation report. However, I want our last run of the document to be as late as possible to get as many possible implementations included.
- Outstanding issues on tracker: none
- Document ready for internal review: April 4 (Staged: https://dvcs.w3.org/hg/prov/raw-file/default/reports/NOTE-prov-implementations-20130430/Overview.html)
- Reviewers: please volunteer, to be finalized at teleconference
- Reviews complete by: April 11
- Changes incorporate by: April 15
- Final vote: 18 April 2013 (last teleconference before staging deadline)
- Final staging: 23 April 2013
Other Tasks
Who is taking leadership for what? What is the timetable?
Namespace
HTML pages
Provenance of documents
- Participants: Luc
- Tim to aggregate and review prov-o's prov