ACT project plan

From Automated WCAG Monitoring Community Group
Jump to: navigation, search

This page has been moved to https://www.w3.org/WAI/GL/task-forces/conformance-testing/wiki/Month_by_month_plan. This version will not be maintained further.

Phase 1

Month Activities
1-2 Develop ACT-Fr requirements & ACT-Fr draft 1
3 TF approval: ACT-Fr Req. & Draft 1
4 WG approval: ACT-Fr Req. & Draft 1
5 Public review: ACT-Fr Req. & Draft 1
5-8
  • Develop ACT-Fr draft 2
  • Develop requirements for ACT Benchmark & ACT Suite
9 TF Approval: ACT-FT draft 2 + req. for Benchm. & Suite
10 WG Approval: ACT-FT draft 2 + req. for Benchm. & Suite
11 Public review: ACT-FT draft 2 + req. for Benchm. & Suite

Phase 2

Month Activities
11-13 Develop ACT-Fr Draft 3 (Last call) + Benchm. method draft 1
14 TF Approval: ACT-Fr Draft 3 + Benchm. Method draft 1
15 WG Approval: ACT-Fr Draft 3 + Benchm. Method draft 1
16 Public review: ACT-Fr Draft 3 + Benchm. Method draft 1
16-19 Develop Benchm. draft 2 + ACT Ruleset PoC v1
20 TF Approve: Benchmark draft 2 + ACT Ruleset PoC v1
21 WG Approve: Benchmark draft 2 + ACT Ruleset PoC v1
22 Public review: Benchmark draft 2 + ACT Ruleset PoC v1
20-22 Develop ACT-Fr draft 4 (Candidate Rec) + Suite requirements v2
23 TF approval: Draft 4, Suite req v2
24 TF approval: Draft 4, Suite req v2
25 Public review: Draft 4, Suite req v2

Phase 3

Month Activities
25-30
  • Implementation & validation ACT Ruleset PoC v2
  • Implement Benchmark
  • Implement ACT Suite
31 Document implementation of ACT Rules
32 Exit CR
33-35 ACT-Fr Proposed Recommendation
36 ACT-Fr Recommendation