Project plan

From W3C Unified Service Description Language
Jump to: navigation, search

The work in the USDL XG is split along 3 main pillars: Related work analysis, specification and evaluation. This can also be seen from the project plan:

Error creating thumbnail: Unable to save thumbnail to destination

The biggest milestone is Milestone 2 at the end of February, because work on USDL continues SAP-internally until then. Beginning of March, this specification will be handed over to the USDL XG for further refinement.

Work packages

  1. WP1: Related work analysis
  2. WP2: Specification of USDL
  3. WP3: Proof-of-concept phase
  4. WP4: Administration

Deliverables

  • D1: „Report on landscapes of existing service technologies“
  • D2.1: “Requirements on a standard specification”
  • D2.2: “Formal specification of the language (USDL XG Version)”
  • D3.1: “Specification of reference test cases”
  • D3.2: “Implementation of reference test cases”
  • D3.3: “Evaluation Result and remarks for USDL rework”
  • D4: „Report on communication and administration activities“

Milestones

  • Milestone 1 (end of 12/2010)
    • Related work finished (T1.1 – T1.4)
    • Requirements finished (T2.1)
    • D1
  • Milestone 2 (end of 02/2011)
    • Requirements on the standardization format elaborated (T2.2)
    • Begin of USDL rework (T2.3), TEXO work on USDL will be finished in USDL M5 Spec
    • D2.1, D3.3
  • Milestone 3 (end of 05/2011)
    • Major rework of USDL done
    • Reference cases identified, implementation begins
    • D3.1
  • Milestone 4 (end of XG, 09/2011)
    • Final report and decision how to proceed
    • D2.2, D3.2, D4