Planning/Plan

From Education & Outreach

Overview

Stage Deliverables/Goals Duration Available for review Reviewed by Review goals
Review existing material
  • Approval resource requirements and audience
  • Approval of approach
19 - 26 Oct 23 Oct 30 Oct
  • Requirements are sufficient
  • Audiences are realistic and comprehensive
  • Audience needs are complete
  • Approach will meet audience needs and communicate material effectively
Design
  • Create visual design mockup
  • Approval of design approach
23 Oct - 3 Nov 30 Oct 13 Nov
  • Accessibility
  • Consistency with WAI style
  • Will support the content needs (note: some sample content is available to explore this)
Code
  • Create coding framework
  • QA of code
28 Oct - 13 Nov 6 Nov 13 Nov
  • Accessibility
  • Code quality
Content
  • Write content for all sections of document
  • QA of content
2 - 27 Nov 13 Nov, 20 Nov, 27 Nov 19 Nov, 26 Nov, 3 Dec
  • Meet the needs of audiences
  • Clearly explain strategic management topics
  • Consistency with WAI style
  • Grammar, spelling, style
Rework content
  • Respond to comments
16 Nov - 10 Dec ?? ??
  • ??
External review
  • ??
N/A 10 Dec 25 Dec
  • ??
Final approval to publish
  • ??
25 Dec 25 Dec
  • ??
Deploy
  • Prepare deliverables for live site
  • Check links
  • Update navigation
  • Publish
4 - 5 Jan 2016 N/A N/A
  • ??

Plan

Stage Task Description Estimated effort Resource Start date End date
Review existing
  Review live documents
  • Determine how documents are used in Roadmap
  • Ensure that everything from Strategy is included in Roadmap
  • Review 'Key actions' for additional topics
  • Review 'Key actions' for usable content
4d Editor
  Review audiences
  • Are audiences comprehensive enough?
  • Are inappropriate audiences included?
  • Are audience needs realistic and comprehensive?
1d EO
  Review existing prototype
  • Consider design style in light of Tips
  • Does approach adequately meet audiences
  • Consider if additional navigation options are necessary
1d EO
  Approve broad approach
  • Editor and PM to approve prior to EO
1h Editor, PM, EO
Design
  Create design wireframes
  • Incorporate feedback from review phase
  • Develop complete style guide for resource
3d Editor
  Review wireframes 1h EO
  Update wireframes 1d Editor
  Approve designs
  • Editor and PM to approve prior to EO
  • Approval must be received before Code phase
1h Editor, PM, EO
Code
  Develop coding framework for design 2d Editor
  Cross-browser testing
  • Last three versions of major browsers: IE, FF, Chrome, Safari, Opera(?)
  • Latest version of Mac OSX
  • Windows 8.1, 10
  • Mobile? (Latest iOS, Android (?), browsers?)
1d Editor, EO
  Assistive technology testing
  • ??
1d Editor, EO
Content
  Introduction 1.5d Editor
  Initiate
  • Review and rewrite existing content
  • May need expanding if additional topics added
2.5d Editor
  Plan 5.5d Editor
  Implement 4d Editor
  Monitor 3d Editor
  Tag topics
  • Develop tags
  • Assign tags
1.5d Editor
  Improving document 0.5d Editor
  Policies document 0.5d Editor
  Acknowledgements 0.5d Editor
Internal review
  Introduction 1d EO
  Initiate 1d EO
  Plan 1d EO
  Implement 1d EO
  Monitor 1d EO
  Improving document 1d EO
  Policies document 1d EO
External review
  ??
Approval
  Final approval to publish 1h EO
Deploy
  Prepare roadmap to deploy
  • Adjust primary navigation
  • Change status
  • Update acknowledgements page
  • Check links
1d Editor
  Prepare improving and policies to deploy
  • Adjust primary navigation
  • Change status
  • Update acknowledgements page
  • Check links
0.5d Editor
  Deploy 1h Editor