The topic of Device Independence is of long term concern, and it may be expected that its charter will be renewed or extended from time to time. The first charter of the group covered the period from February 2001 to February 2002. The second charter covered the period from February 2002 to the end of October 2004.
The third charter is intended to cover the two year period from the beginning of November 2004 to the end of October 2006.
For the work items described above, the key milestones are illustrated in the following table:
Work Item | 11/04 | 12/04 | 01/05 | 02/05 | 03/05 | 04/05 | 05/05 | 06/05 | 07/05 | 08/05 | 09/05 | 10/05 | 11/05 | 12/05 | 01/06 | 02/06 | 03/06 | 04/06 | 05/06 | 06/06 | 07/06 | 08/06 | 09/06 | 10/06 |
Delivery Context Overview | Note | |||||||||||||||||||||||
CC/PP S&V V 1.1 | Rqmts | 1st WD | LC WD | REC (*) | ||||||||||||||||||||
CC/PP Processing and Protocol V 1.0 | Rqmts | 1st WD | LC WD | REC (*) | ||||||||||||||||||||
Core Presentation Characteristics V 1.0 | 1st WD | LC WD | REC (*) | |||||||||||||||||||||
Language Profile for DI V 1.0 | 1st WD | Working Draft | LC WD | REC (*) | ||||||||||||||||||||
Selection for DI V 1.0 | 1st WD | LC WD | REC (*) | |||||||||||||||||||||
Layout for DI V 1.0 | Rqmts | 1st WD | LC WD | REC (*) | ||||||||||||||||||||
Aggregation & Decomposition for DI V 1.0 | Rqmts | 1st WD | LC WD | REC (*) | ||||||||||||||||||||
Semantic Enrichment | Investigation | Rqmts | 1st WD | LC WD | REC (*) | |||||||||||||||||||
Metadata for Content Adaptation V 1.0 | Investigation | Wkshp | Rqmts | 1st WD | LC WD | REC (*) | ||||||||||||||||||
Dynamic Properties Framework | out of DIWG | pre-DIWG LC issues management | 2nd LC WD | REC (*) | ||||||||||||||||||||
Errata | Maintenance |
(*): REC covers all the process roadmap from CR to REC
Type of Work | Color Code |
---|---|
Work on the W3C Recommendation Track | |
Work Leading to a W3C Note | |
A Workshop | |
Ongoing Work | |
Work on the W3C Recommendation Track potentially outside DIWG | |
Work within DIWG charter but no ressource/expertise available for now. may be transferred to other groups |
It is expected that parallel work items will be addressed by informal subgroups of the DI WG, with significant overlap of participation. Coordination will be maintained by regular meetings involving the whole group.
Other events are as follows: